Boloco
FAILTuesday, April 10, 2012 at 3:31 PM
Violations Cited
03-3-501.14
Cooling
The black beans and the pinto beans in the cooler are in large containers and are 46F in the center and 41F along the edges. Ensure that these are getting properly cooled from 140F to 70F in two hours and then from 70F to 41F in an additional four hours. (The manger discarded the beans and will retrain the staff about cooling and verify the process with temperature logs.)
Why This Matters
This violation directly contributes to foodborne illness risk
Code Requirements
Immediate correction required. Follow health code section . Implement proper food safety procedures. Train all staff. Document corrective actions taken.
27-5-103.11-.12
Hot and Cold Water
The hot water took a few minutes to get hot. Make sure the water is hot quickly so employees can easily wash their hands.
Why This Matters
This violation directly contributes to foodborne illness risk
Code Requirements
Immediate correction required. Follow health code section . Implement proper temperature control procedures. Train all staff. Document corrective actions taken.
17-4-302.14
Test Kit Provided
There are no test strips. Provide.
Why This Matters
This violation affects overall sanitation and food safety
Code Requirements
Immediate correction required. Follow health code section . Implement proper food safety procedures. Train all staff. Document corrective actions taken.
37-6-501.11-.12
Improper Maintenance of Walls/Ceilings
The hood vent is due for a cleaning. Have the vent cleaned by a licensed company.
Why This Matters
OVERHEAD CONTAMINATION: Peeling paint and debris fall into food. Condensation on ceilings drips bacteria onto prep surfaces. Studies found ceiling tiles harbor Bacillus cereus spores. Restaurant ceiling collapse contaminated food service for 200 guests.
Code Requirements
Walls/ceilings must be: Smooth and washable in food areas; Light-colored for easy soil detection; Free of holes, cracks, peeling paint; Sealed at all joints and attachments; Clean and free of grease, dust, cobwebs; Non-absorbent in areas subject to moisture.
Corrective Actions
Repair all holes within 14 days; Repaint with washable paint; Replace damaged ceiling tiles; Seal all penetrations; Clean walls and ceilings monthly; Fix any leaks immediately; Install FRP panels in splash zones