Fisherman's Net
FAILMonday, August 27, 2012 at 5:52 PM
Violations Cited
03-3-501.16
Hot Holding
Stuffed clams 91F and 95 F Crab Cakes 105 F Scallops 85 F
Why This Matters
This violation directly contributes to foodborne illness risk
Code Requirements
Maintain all hot TCS foods at 135°F or above; Cannot use hot holding equipment to reheat
M-2-102.11
PIC Knowledge
Certifed food protection manager not certified in Allergen Awareness.
Why This Matters
This violation directly contributes to foodborne illness risk
Code Requirements
Immediate correction required. Follow health code section . Implement proper management & personnel procedures. Train all staff. Document corrective actions taken.
08-3-305-307.11
Food Protection
Walk in 47 °F
Why This Matters
This violation affects overall sanitation and food safety
Code Requirements
Immediate correction required. Follow health code section . Implement proper food safety procedures. Train all staff. Document corrective actions taken.
17-4-204.112/.115
Equipment Thermometers
Provide working thermometer in walk in refrig.
Why This Matters
This violation affects overall sanitation and food safety
Code Requirements
Immediate correction required. Follow health code section . Implement proper equipment procedures. Train all staff. Document corrective actions taken.
37-6-501.11-.12
Improper Maintenance of Walls/Ceilings
Clean walls and attachments
Why This Matters
OVERHEAD CONTAMINATION: Peeling paint and debris fall into food. Condensation on ceilings drips bacteria onto prep surfaces. Studies found ceiling tiles harbor Bacillus cereus spores. Restaurant ceiling collapse contaminated food service for 200 guests.
Code Requirements
Walls/ceilings must be: Smooth and washable in food areas; Light-colored for easy soil detection; Free of holes, cracks, peeling paint; Sealed at all joints and attachments; Clean and free of grease, dust, cobwebs; Non-absorbent in areas subject to moisture.
Corrective Actions
Repair all holes within 14 days; Repaint with washable paint; Replace damaged ceiling tiles; Seal all penetrations; Clean walls and ceilings monthly; Fix any leaks immediately; Install FRP panels in splash zones